The Project
LSG Building Solutions GmbH was contractedtorealizethe20/110kV power station incl. transformer and 110kV overhead-line for theproject photovoltaik-powerplant „BETA“.

Although differing in size and investment costs, projects Alpha, Beta and Gamma employed largely the same technology. Mounted with Schüco technology, the modules are each fixed at a 25° angle to grant maximum performance yield and minimum shading. Distance between the module rows is 7.5 meters. Cabling was supplied by MeinhartKabel, which was installed underground in a sand bed. SMA supplied its Sunny Central inverters for the project (models CP-720, CP-800 and CP-850 were used), with skytron’s monitoring system employed across all three projects as part of Green Source’s O&M management.

 

Scope of Work
Delivery, installation and commissioning of:
20kV-indoor switchgear
110kV- outdoor-switchgear
25MVA transformer20/110kV
SCADA-control
Civilworks (buildings, fences, streets, foundations)
Auxiliary installations for Station buildings

 

Key Figures
Name:                           Beta
Voltage niveau:           20 / 110 kV
Total Power Station:   20 MW
Completion:                October 2013
Cost:                             € 34 million ($46 million)
CO2 savings:                Approx. 18,000 metric tons per year
Modules used:              Risen
Investment partner:    Risen

The Client
LJG Green Source Energy Beta srl

 

 

 

The Project
LSG Building Solutions GmbH was contractedtorealizethe20/110kV power station incl. transformer and 110kV overhead-line for theproject photovoltaik-powerplant „BETA“.

Although differing in size and investment costs, projects Alpha, Beta and Gamma employed largely the same technology. Mounted with Schüco technology, the modules are each fixed at a 25° angle to grant maximum performance yield and minimum shading. Distance between the module rows is 7.5 meters. Cabling was supplied by MeinhartKabel, which was installed underground in a sand bed. SMA supplied its Sunny Central inverters for the project (models CP-720, CP-800 and CP-850 were used), with skytron’s monitoring system employed across all three projects as part of Green Source’s O&M management.

 

Scope of Work
Delivery, installation and commissioning of:
20kV-indoor switchgear
110kV- outdoor-switchgear
25MVA transformer20/110kV
SCADA-control
Civilworks (buildings, fences, streets, foundations)
Auxiliary installations for Station buildings

 

Key Figures
Name:                           Beta
Voltage niveau:           20 / 110 kV
Total Power Station:   20 MW
Completion:                October 2013
Cost:                             € 34 million ($46 million)
CO2 savings:                Approx. 18,000 metric tons per year
Modules used:              Risen