Cineplexx Group commissioned the complete execution of high and low voltage installations equipping 5 cinema auditoriums with a total of 850 seats in the Stop Shop in Niš.

Scope of Works
The investor decided to build on a total area of 2.000 m2 cinemas with the latest digital image projection and sound technology of the most modern generation.

Key Indicators
Surface area:                                                      2.000 m2
Cable laid:                                                         40 000 m
Total installed lights:                                         380 pcs
Recessed lights in the foyer:                               30 pcs
Lighting fixtures LED GRADUS:                       150 m
Lighting fixtures LED H:                                     170 m
Total energy capacity :                                      220 kW

Highlights
On this project 40 electricians worked simultaneously so that all the works could be completed in less than 3 months.

Completion
11/2016.

Investor
Cineplexx SRB d.o.o.

Project
Cineplexx Group commissioned the complete execution of high and low voltage installations equipping 5 cinema auditoriums with a total of 850 seats in the Stop Shop in Niš.

Scope of Works
The investor decided to build on a total area of 2.000 m2 cinemas with the latest digital image projection and sound technology of the most modern generation.

Key Indicators
Surface area:                                                      2.000 m2
Cable laid:                                                         40 000 m
Total installed lights:                                         380 pcs
Recessed lights in the foyer:                               30 pcs
Lighting fixtures LED GRADUS:                       150 m
Lighting fixtures LED H:                                     170 m
Total energy capacity :                                      220 kW

Highlights
On this project 40 electricians worked simultaneously so that all the works could be completed in less than 3 months.

Completion
11/2016.