#ADVANCEDSOLUTIONSFORABETTERLIFE!  

Cineplexx Nis

Cineplexx Nis

Investor

Cineplexx SRB d.o.o.

 

Project

Cineplexx Group commissioned the complete execution of high and low voltage installations equipping 5 cinema auditoriums with a total of 850 seats in the Stop Shop in Niš.

 

Scope of Works

The investor decided to build on a total area of 2.000 m2 cinemas with the latest digital image projection and sound technology of the most modern generation.

 

Key Indicators

Surface area:                                                      2.000 m2

Cable laid:                                                         40 000 m

Total installed lights:                                         380 pcs

Recessed lights in the foyer:                               30 pcs

Lighting fixtures LED GRADUS:                       150 m

Lighting fixtures LED H:                                     170 m

Total energy capacity :                                      220 kW

 

Highlights

On this project 40 electricians worked simultaneously so that all the works could be completed in less than 3 months.

 

Completion

11/2016.

Investor

Cineplexx SRB d.o.o.

 

Project

Cineplexx Group commissioned the complete execution of high and low voltage installations equipping 5 cinema auditoriums with a total of 850 seats in the Stop Shop in Niš.

 

Scope of Works

The investor decided to build on a total area of 2.000 m2 cinemas with the latest digital image projection and sound technology of the most modern generation.

 

Key Indicators

Surface area:                                                      2.000 m2

Cable laid:                                                         40 000 m

Total installed lights:                                         380 pcs

Recessed lights in the foyer:                               30 pcs

Lighting fixtures LED GRADUS:                       150 m

Lighting fixtures LED H:                                     170 m

Total energy capacity :                                      220 kW

 

Highlights

On this project 40 electricians worked simultaneously so that all the works could be completed in less than 3 months.

 

Completion

11/2016.