Hotel Diadora

Hotel Diadora

Client
Punta Skala d.o.o.

Project
Falkensteiner Family Hotel Diadora is an exclusive family hotel within the Punta Skala Resort, which was upgraded from a 4-star hotel to a 5-star hotel during the reconstruction.

Scope of Services
LSG Building Solutions d.o.o. was in charge of the complete reconstruction of electrical and mechanical installations together with accompanying plasterboard works with the aim of upgrading to a 5-star hotel. The reconstruction included 249 rooms, as well as the public areas of the reception and lobby, restaurant, bar, softplay game room, SPA area, public toilets and terrace.

Key Figures
Number of rooms: 249 rooms
Surface areas of standard rooms: 33-37 m2
Suite areas: 43-56 m2
Approx. 7,000 m2 of plasterboard walls and cladding + suspended ceilings in all rooms
Approx 60 km of electrical installation cables (dismantling of existing ones and creation of new installation)
249 sets of bathrooms – complete dismantling of existing sanitary elements with all plumbing and sewage installations and construction of new
renovation of ventilation, heating and cooling systems in all rooms
2,000 m2 of suspended ceilings in the corridors with replacement of lighting fixtures and ventilation grilles in them
Dismantling of existing and performing all new installations in public spaces

Highlights
Execution of complete reconstruction works in just 6 months – during the winter period.

Completion
06/2022

Client
Punta Skala d.o.o.

Project
Falkensteiner Family Hotel Diadora is an exclusive family hotel within the Punta Skala Resort, which was upgraded from a 4-star hotel to a 5-star hotel during the reconstruction.

Scope of Services
LSG Building Solutions d.o.o. was in charge of the complete reconstruction of electrical and mechanical installations together with accompanying plasterboard works with the aim of upgrading to a 5-star hotel. The reconstruction included 249 rooms, as well as the public areas of the reception and lobby, restaurant, bar, softplay game room, SPA area, public toilets and terrace.

Key Figures
Number of rooms: 249 rooms
Surface areas of standard rooms: 33-37 m2
Suite areas: 43-56 m2
Approx. 7,000 m2 of plasterboard walls and cladding + suspended ceilings in all rooms
Approx 60 km of electrical installation cables (dismantling of existing ones and creation of new installation)
249 sets of bathrooms – complete dismantling of existing sanitary elements with all plumbing and sewage installations and construction of new
renovation of ventilation, heating and cooling systems in all rooms
2,000 m2 of suspended ceilings in the corridors with replacement of lighting fixtures and ventilation grilles in them
Dismantling of existing and performing all new installations in public spaces

Highlights
Execution of complete reconstruction works in just 6 months – during the winter period.

Completion
06/2022