Client
Stadt Wien / Vienna Hospital Association

Project
In the new Annex to the hospital Rudolfstiftung, a data Center of the Vienna Hospital Association was housed. The contract essentially included the supply and Installation of internal server cabling using blown fiber and twisted-pair cables, the supply of Network cabinets, including Monitoring and their electrical Connection to the uninterruptible power supply System of the hospital.

Scope of Services
Supply and Installation of Server racks
passive IT infrastructure (blownfiberandtwisted pair)
Electrical supply to the Server racks
Energy Monitoring and network analysis
Server cabinet monitoring
Supply and Installation of the server rack cooling
Supply and Installation of cold aisle enclosures
Access control system

Key Figures
Straddle cooling power: 112kW
blown 12x opticalfiber: 23km
Electrical power: approx 1MW
Fiber Connection Points: 26,500
Completion Date: 02/2015

Highlights
With the short construction period, the passive infrastructure to accommodate the new KAV data center was implemented in less than a year. During the construction period, the existing Server infrastructure was moved.

Client
Stadt Wien / Vienna Hospital Association

Project
In the new Annex to the hospital Rudolfstiftung, a data Center of the Vienna Hospital Association was housed. The contract essentially included the supply and Installation of internal server cabling using blown fiber and twisted-pair cables, the supply of Network cabinets, including Monitoring and their electrical Connection to the uninterruptible power supply System of the hospital.

Scope of Services
Supply and Installation of Server racks
passive IT infrastructure (blownfiberandtwisted pair)
Electrical supply to the Server racks
Energy Monitoring and network analysis
Server cabinet monitoring
Supply and Installation of the server rack cooling
Supply and Installation of cold aisle enclosures
Access control system

Key Figures
Straddle cooling power: 112kW
blown 12x opticalfiber: 23km
Electrical power: approx 1MW
Fiber Connection Points: 26,500
Completion Date: 02/2015

Highlights
With the short construction period, the passive infrastructure to accommodate the new KAV data center was implemented in less than a year. During the construction period, the existing Server infrastructure was moved.