AS an extension of the existing BESS project in Senyo, a new 75 MWh energy storage capacity is bein installed, with a 0.25 charge/discharge rate.
The new system will be connected, just like the existing one, to the 22/132 kV transformer station of the Senyo PV plant. To facilitate this, a new medium-voltage (MV) cell will be installed.
Our partnership with HITHIUM for the supply of BESS containers continues, reflecting a strong and consistent collaboration.
We are also pleased to announce a new partnership with SOFAR for the delivery of medium-voltage power stationsm marking our first project with them.