Client
Wien Energie GmbH
Contractor
LSG Solar Solutions GmbH
Project
In 2015, 6 sections of the photovoltaic power plant Guntramsdorf with a total output of 2034 kWp were erected.
In the period from May to July 2019 the power plant was expanded. In addition to the existing six sections, four more with a total output of 1360 kWp were installed.
In total 3.4 MWp have been installed at the location Guntramsdorf on an area of approx. 6.7 hectares.
Scope of Services
Engineering of the project
Cable loss analysis
Project planning, incl. drawings
Static calculation
Delivery, Installation Supervision and Commissioning
PV Modules
Substructure
Inverters
Pile ramming tests
Substation 0,4 kV
AC and DC cabling, incl. fuses
Fencing incl. CCTV
Wireless data communication network
Key data
Voltage Level: 0,4 kV
Installed Capacity: 6,7 MWp / 3,1 MVA
CO2 Savings: 1347 t/year